TPW20-0238 Glengarry Street, Woodville South

Project type
Pipeline
Client
SA Water
Date Complete
December, 2021
Location
Glengarry Street, Woodville South

TPW20-0238 Glengarry Street, Woodville South

Team Civil engaged as part of a SA Water fast-tracked program requiring works to be completed as soon as possible.

Scope of works performed:

The works associated with Bridge Road, Payneham works included the following, but not limited to:

  • Team Civil engaged as part of a SA Water fast-tracked program requiring works to be completed as soon as possible.
  • Advance notice of works provided to nearby properties (SA Water Customers).
  • Liaison with Allwater for the shutdown of water mains.
  • Notice was given to Allwater 10 working days before construction.
  • Liaison and coordination with Greenhill, the site contractor.
  • Hand chlorination of new water main and fittings.
  • Supply of water tanker to maintain water supply to a medical centre during shutdown.
  • 3 x DN100 water main dog legs.
  • 1 x water services reconnected.
  • Supply of all materials & traffic management.
  • Updated supplied CAD drawings to as constructed status.