Kingscote KI Depot – Earth, Basin & Stormwater Swale

Project type
Road & Earthworks, Water
Client
SA Water
Date Complete
April, 2026
Location
Kingscote, Kangaroo Island

Kingscote Depot - Earth basin and stormwater swale

Engaged to deliver a comprehensive stormwater infrastructure upgrade at the site. The completed works significantly improved stormwater management across the depot, reducing flood risk to adjacent properties, enhancing operational functionality, and delivering a compliant, sustainable drainage solution aligned with SA Water standards.

Scope of works performed:

Team Civil was engaged to conduct the following

  • Site establishment and preparation, including mobilisation, service locating, demolition and removal of existing concrete and bitumen as required.
  • Construction of a 75kL detention basin to capture and manage stormwater runoff from the depot’s roof and site catchments.
  • Installation of new stormwater infrastructure, including pits, pipelines, swales, spoon drains and culvert crossings, connecting to existing DN150, DN250 and DN300 drainage networks.
  • Southeast catchment upgrades, including removal of the existing 27kL overflow tank, redirection of Tank 5 and 6 overflows, new swales, a 10m overflow weir and riprap scour protection.
  • Northeast catchment upgrades, including 450mm spoon drains, grass-lined swales, check dams and a 600mm x 150mm culvert crossing beneath the access track.
  • Southwest catchment upgrades, including grass-lined swales and a new pit and pipe network connecting to existing DN250 infrastructure and the detention basin.
  • Reinstatement and project completion, including access track upgrades, scour protection, hydroseeding, final reinstatement, site clean-up, demobilisation and submission of QA documentation to SA Water.