South Para Culvert Crossing

Project type
Water
Client
SA Water
Date Complete
December, 2022
Location
South Para Reservoir

South Para Culvert Crossing

As part of the Opening Up Reservoirs scheme SA Water engaged Team Civil to provide design input and construct a culvert crossing and hiking trail to offer further access within South Para Reservoir for hikers to experience. 

Scope of works performed:

Scope of works performed at South Para Reservoir were as follows:

  • Mobilise to site and set up temporary facilities.
  • Upgrade access track, storage, and turn-around area, ensuring delivery trucks can reach work zone.
  • Carefully delineate work zone via flagging, in consultation with SA Water representatives.
  • Install sediment and erosion control devices downstream of works.
  • Clear and grub all vegetation strictly within the agreed delineated work zone.
  • Excavate and prepare base at location of new concrete culverts and headwalls including:
    –  Upstream reinforced concrete cut-off wall.
    –  Upstream and downstream rock lined weirs.
    –  Concrete bed, 100mm thick nominally, to culvert invert with randomly placed D350 rock, creating the fishway structure.
    –  Rock armouring of headwalls.
  • Construct rock lined swale from existing DN900 MSCL pipe under fire track to river.
  • Build-up and rock armour sub-base of hiking track either of culverts to underside of hiking track, enabling connection of the two banks of the river by the track.
  • Construct hiking track using cement treated quarry rubble.
  • Manage minor river flows through the works.
  • Remove all flagging, sediment, and erosion control measures from river.
  • Clean up site and remove any temporary facilities.
  • Leave access road and turnaround in place for use by Forestry SA